Solution = 2 platforms on 1 mast tower.
PHD were called upon to surmount a challenge where 2 adjoining builds clashed !!

Bovis Construction were building adjacent to John Sisk Contractors  Hotel Project –

The problem was the block they were building  was  12 # floors higher and would not complete before the Hotel opened.

Access would have to be over the hotel and there was a problem over air rights.

The incumbent scaffold contractor proposed a Beam Bridge system which blew the budget and could not be completed in the time available.

PHD designed a truss out cantilever system onto which they sat their 3,000Kg capacity mast climber and mounted 2 separate platforms on one mast.

This allowed  different trades to work on the same elevation at the same time.

This meant the client could catch up on programme, avoid penalties and save against the more expensive  and time consuming beam bridge solution.

For more information see PHD Hoists and Masts.